Get-in days 1 and 2 done.

Day 1 (8 hours) – Thanks to the team, we rigged all of the lighting over the stage, installed the Sound Booth and projectors, painted the stage and got everything prepared for the arrival of the set.

Day 2 (12 hours) – Snow appeared today, as did the set lorry.
The portals, cloths and banners are all on their bars, plus 5 out of the 6 pieces of masking.
All other lighting is now rigged.
DSM desk and comms all set up.
Sound equipment was installed and configured.

The photo was taken at the end of day one and shows the LX that was rigged and the crew giving the stage a fresh coat of paint before the set arrived.